Sub-center not built even after eight years

hear the news

hear the news

Sub-center not built even after eight years
Farrukhabad. The construction of one of the two substations approved eight years ago to overcome the electricity crisis has not yet started. After the incomplete construction of the second, the tube well feeder was put into operation. The line was not even laid for Sankisa and rural areas. Unfinished substations often increase the load on old substations. As a result, there is a power crisis in the villages.
In order to supply rural areas with uninterrupted electricity, Naugawan in Jahanganj, Pahala in Kamalganj and substations in the village of Sankisa in Merapur have been approved. The work organization Ishaan Earthing was responsible for the construction.
The construction of all three substations should be completed in three years. By connecting villages to these substations, the load on the old substations is reduced. Even after eight years, construction of the sub-center in the village of Pahala has not even started.
Three feeders were to be built in the Sankisa substation. Only Paramkheria PTW (Nalcool Line) was built and inaugurated in October 2020. The power line from Paramkhiriya Rural and Sankisa Feeder, 33 KV line from Pakhna to Nibkarori transmission has not yet been built.
This will supply the villages around Sankisa, Paramkhiria with electricity from the old substations. You are also overloaded. There is a power crisis in the villages. With the completion of the Naugawan substation, it went into operation in February 2021.
what is responsible
“The work organization was asked to complete the ongoing work on the Sankisa substation by August. A notification was sent to the company owner for this as well. The contract for the first substation was canceled. The tender will be carried out again. Sudhir Srivastava, SDO Construction Department Electricity Kanpur
Frequent faults in lines
Farrukhabad. With the population growth in the metropolitan areas, the number of electricity consumers has also increased significantly. Due to the increased demand, the power supply in the substations has also increased. If the capacity of substations is not increased, disruptions due to overloading often occur. In the scorching heat, consumers have to bear the brunt of the burden. Even after an uninterrupted supply from the power plant, people only get a few hours of electricity.
Electricity is delivered to 15 locations including Court, Collectorate, Officers Colony, Civil Lines from the Kutra substation in the city area. Most of the district’s top officials and elites have residences under the jurisdiction of this substation.
About 10 villages and 15 localities are supplied with electricity from the Panchal Ghat substation. Private hospitals have more connections from this sub-center. Both substations are overloaded for many years. Transformer breakdowns and burnouts happen every day.
In order to increase the capacity of the two substations, a proposal was made and sent to install two transformers of five MVA. Due to the non-implementation of the proposal, the capacity of both substations will remain the same. Both substations groan because of overload. Due to the frequent failure of the substation due to frequent malfunctions, there is a power failure several times a day. Consumers are upset because electricity is blinded due to disruption in urban areas.
what is responsible
“A proposal was sent to increase the capacity of two substations. Once the proposal is accepted, the job is done. Another letter is written to the officials. RB Yadav, Xen Urban
Photo – 7 and 8
15 power poles in dangerous places were removed
Farrukhabad. On the city’s main street, work was carried out to remove the electricity pylons that host the accident. All bars are removed by evening. About 20 masts were installed in the city from the housing estate to Nekpur Chaurasi. Accidents were often caused by vehicles colliding with these masts. The unloading of the cables from these masts began a month ago. Later the work was stopped. Five poles were removed 15 days ago. On the austerity of XEN Urban, 15 masts were removed for contractor Rohit Yadav on Sunday. Xen Urban RB Yadav said all bars were removed.

Sub-center not built even after eight years

Farrukhabad. The construction of one of the two substations approved eight years ago to overcome the electricity crisis has not yet started. After the incomplete construction of the second, the tube well feeder was put into operation. The line was not even laid for Sankisa and rural areas. Unfinished substations often increase the load on old substations. As a result, there is a power crisis in the villages.

In order to supply rural areas with uninterrupted electricity, Naugawan in Jahanganj, Pahala in Kamalganj and substations in the village of Sankisa in Merapur have been approved. The work organization Ishaan Earthing was responsible for the construction.

The construction of all three substations should be completed in three years. By connecting villages to these substations, the load on the old substations is reduced. Even after eight years, construction of the sub-center in the village of Pahala has not even started.

Three feeders were to be built in the Sankisa substation. Only Paramkheria PTW (Nalcool Line) was built and inaugurated in October 2020. The power line from Paramkhiriya Rural and Sankisa Feeder, 33 KV line from Pakhna to Nibkarori transmission has not yet been built.

This will supply the villages around Sankisa, Paramkhiria with electricity from the old substations. You are also overloaded. There is a power crisis in the villages. With the completion of the Naugawan substation, it went into operation in February 2021.

what is responsible

“The work organization was asked to complete the ongoing work on the Sankisa substation by August. A notification was sent to the company owner for this as well. The contract for the first substation was canceled. The tender will be carried out again. Sudhir Srivastava, SDO Construction Department Electricity Kanpur

Frequent faults in lines

Farrukhabad. With the population growth in the metropolitan areas, the number of electricity consumers has also increased significantly. Due to the increased demand, the power supply in the substations has also increased. If the capacity of substations is not increased, disruptions due to overloading often occur. In the scorching heat, consumers have to bear the brunt of the burden. Even after an uninterrupted supply from the power plant, people only get a few hours of electricity.

Electricity is delivered to 15 locations including Court, Collectorate, Officers Colony, Civil Lines from the Kutra substation in the city area. Most of the district’s top officials and elites have residences under the jurisdiction of this substation.

About 10 villages and 15 localities are supplied with electricity from the Panchal Ghat substation. Private hospitals have more connections from this sub-center. Both substations are overloaded for many years. Every day there are malfunctions and burned out transformers.

In order to increase the capacity of the two substations, a proposal was made and sent to install two transformers of five MVA. Due to the non-implementation of the proposal, the capacity of both substations will remain the same. Both substations groan because of overload. Due to the frequent failure of the substation due to frequent malfunctions, there is a power failure several times a day. Consumers are upset because electricity is blinded due to disruption in urban areas.

what is responsible

“A proposal was sent to increase the capacity of two substations. Once the proposal is accepted, the job is done. Another letter is written to the officials. RB Yadav, Xen Urban

Photo – 7 and 8

15 power poles in dangerous places were removed

Farrukhabad. On the main street of the city, work was carried out to remove the electricity pylons that had caused the accident. All bars are removed by evening. About 20 masts were installed in the city from the housing estate to Nekpur Chaurasi. Accidents were often caused by vehicles colliding with these masts. The unloading of the cables from these masts began a month ago. Later the work was stopped. Five poles were removed 15 days ago. On the austerity of XEN Urban, 15 masts were removed for contractor Rohit Yadav on Sunday. Xen Urban RB Yadav said all bars were removed.

.

( News Source – Amar Ujala )