Stp Construction Work Hangs In Balance, Waiting For Pollution Release Kali River

STP under construction at Kasganj.
– Photo : KASGANJ

Kasganj. The initiative being taken to get rid of pollution in Kalindi is getting a setback again and again. The target set twice was not met. Now the claims of the upcoming target are also visible in the air. No date has been fixed for when the working organization, which is claiming to have done the work in the last phase, will get started. Now it is claimed that sewerage treatment will start from this plant by the last days of the first fortnight this month.
The Kali River, which carries drains and waste from industrial areas, has been engulfed by pollution for a long time. In order to free this river from pollution, a sewerage treatment plant is being constructed near Kalindi.
In this treatment plant, the water of two dirty drains which used to fall directly into the Kalindi will now fall into the river after the purification process, but right now the pace of construction of this STP is showing slow. Initially, the department was claiming that the STP construction would be completed in the first fortnight of July and it would be able to treat the sewerage, but after that the target was increased till August. Now after the passing of August, the first fortnight of September is in the last phase. Still, the launch date has not been decided.
From the point of view of statistics-
– STP construction has been approved with Rs 67.56 crore.
STP being built with the capacity to purify 15 million liters of water per day.
– Maintenance will be done after construction with Rs 33.32 crore.
– The executive organization will perform the responsibility of maintenance for 15 years.
STP work is almost complete. The machines have also been almost installed. Soon the water treatment will be started by starting the STP. Gaurav Sharma, Junior Engineer, Pollution Control Unit, Jal Nigam Agra.

Kasganj. The initiative being taken to get rid of pollution in Kalindi is getting a setback again and again. The target set twice was not met. Now the claims of the upcoming target are also visible in the air. No date has been fixed for when the working organization, which is claiming to be working in the last phase, will get started. Now it is claimed that sewerage treatment will start from this plant by the last days of the first fortnight this month.

The Kali River, which carries drains and waste from industrial areas, has been engulfed by pollution for a long time. In order to free this river from pollution, a sewerage treatment plant is being constructed near Kalindi.

In this treatment plant, the water of two dirty drains which used to fall directly into the Kalindi will now fall into the river after the purification process, but right now the pace of construction of this STP is showing slow. Initially, the department was claiming that the STP construction would be completed in the first fortnight of July and it would be able to treat the sewerage, but after that the target was increased till August. Now after the passing of August, the first fortnight of September is in the last phase. Even then the launch date has not been decided.

From the point of view of statistics-

– STP construction has been approved with Rs 67.56 crore.

STP being built with the capacity to purify 15 million liters of water per day.

– Maintenance will be done after construction with Rs 33.32 crore.

– The executive organization will perform the responsibility of maintenance for 15 years.

STP work is almost complete. The machines have also been almost installed. Soon the water treatment will be started by starting the STP. Gaurav Sharma, Junior Engineer, Pollution Control Unit, Jal Nigam Agra.

.

( News Source – Amar Ujala )