Hapur News – track construction for freight trains from October

hear the news

hear the news

The tracks for freight trains will be laid from October
Hapur. The work of the Dedicated Freight Corridor, which is being built for freight trains, has gained momentum in the district. The highway has been closed from one side of the dividing line for the construction of the NH-334 bridge near the Brajnathpur canal bridge on Bulandshahr Street. Then a bridge will be built over the elevated road. The track construction work will begin in October. The aim is to complete the work by June 2022.
The dedicated freight corridor is being built with an investment of around 15,000 billion rupees. This includes 8870 crores for construction, 4,000 crores for land acquisition and 2500 crores for electrification. Most of the construction work for the single trail construction between Khurja and Saharanpur over an area of ​​222 km has been completed. A total of 19 km of track is to be built in Hapur.
71 bridges completed
The construction of 71 bridges of 102 small and large bridges under this corridor in the district has been completed. In which 52 bridges were built over the irrigation canals of the farmers, there are 39 underpasses. There are eight large bridges underneath. One bridge is to be built on the NH 334 and one on Highway 9. Construction of the bridge began with the closure of one side of the NH 334. Then the bridge of Highway-9 will be built.
The altitude is on NH-9. eight meters
The Brijnathpur canal bridge and the bridge on the NH-09 near Nizampur will be built eight meters high. Due to the height of the bridge of eight meters above the road, vehicles can pass easily. Previously the bridge was supposed to be built near Nizampur, but for some reason the construction of the bridge over the Brijnathpur Canal and the adjacent highway has now started.
the work will be completed soon
After the bridge on the 09 and 334 motorways has been built, the rest of the construction work will also be completed. The track construction work will begin in October. Work in the district will be completed by June 2022. However, the process will take time.
– Gurvinder Singh, Construction Manager Executive Organization

The tracks for freight trains will be laid from October

Hapur. The work of the Dedicated Freight Corridor, which is being built for freight trains, has gained momentum in the district. The highway has been closed from one side of the dividing line for the construction of the NH-334 bridge near the Brajnathpur canal bridge on Bulandshahr Street. Then a bridge will be built over the elevated road. The track construction work will begin in October. The aim is to complete the work by June 2022.

The dedicated freight corridor is being built with an investment of around 15,000 billion rupees. This includes 8870 crores for construction, 4,000 crores for land acquisition and 2500 crores for electrification. Most of the construction work for the single trail construction between Khurja and Saharanpur over an area of ​​222 km has been completed. A total of 19 km of track is to be built in Hapur.

71 bridges completed

The construction of 71 bridges of 102 small and large bridges under this corridor in the district has been completed. In which 52 bridges were built over the irrigation canals of the farmers, there are 39 underpasses. There are eight large bridges underneath. A bridge is to be built on the NH 334 and a bridge on Highway 9. Construction of the bridge began with the closure of one side of the NH 334. Then the bridge of Highway-9 will be built.

The altitude is on NH-9. eight meters

The Brijnathpur canal bridge and the bridge on the NH-09 near Nizampur will be built eight meters high. Due to the height of the bridge of eight meters above the road, vehicles can pass easily. Previously the bridge was supposed to be built near Nizampur, but for some reason the construction of the bridge over the Brijnathpur Canal and the adjacent highway has now started.

the work will be completed soon

After the bridge on the 09 and 334 motorways has been built, the rest of the construction work will also be completed. The track construction work will begin in October. Work in the district will be completed by June 2022. However, the process will take time.

– Gurvinder Singh, Construction Manager Executive Organization

.