Amrit Yojna – No change was seen in town, Rs 67 crore washed away in the water

hear the news

hear the news

Rae Bareli. The AMRUT program, which was launched to relieve 2.5 lakh residents of the urban area from the sewerage, was commissioned from the start. The work organization Gharpure got the work instead of working, this executive organization gave work to the Tomar Construction Company.
Complaints about the haphazard work continued to return from the water company to community officials, but the outcome of the operation remained the same. Not only was poor quality pipes used when laying sewers, but poor quality was also used when building roads.
This can be measured by the fact that Rs 67 crore was spent on the system like water, but the system remains the same. The citizens could neither be relieved of the sewer system, nor were the streets allowed to shine.
On Wednesday, not only did the street on Manika Road collapse in the rain, but the lives of passers-by were also saved. The government’s intention was to install a sewer pipe in the city as part of the AMRUT program.
Roads were dug to lay sewers. A budget of Rs 90 crore was made available for this. Approximately Rs 67 crore was spent on the program. Still, step by step, the plan was messed up.
The road was built in Gora Bazar, but it was in a state of disrepair. The bullets came out. Gribshah was abandoned in the east by building a half-finished road. Jal Nigam and Gharpure Company officials have ever investigated Tomar Construction’s work.
Balmukund Mishra, the EO of the municipality at that time, found during several inspections that the pipes laid in the sewer system were of poor quality. The work was stopped. Found a game in road building.
However, later everything was ok. Sunny Singh, XEN of Jalnigam, said that the AMRUT program has received a budget of Rs 90 crore, of which Rs 67 crore has been paid to date.
Sold earth worth lakhs rupees
The officials of the executing organization not only messed up the laying of sewers and construction work, but also sold lakhs’ worth of the land removed during the excavations. Whether XEN or JE from Jalnigam, none of them paid attention to the standard, but kept filling their pockets. The neglect of the officials has resulted in the flagship of the government of the Amrut Scheme succumbing to corruption in the city.
Actions to be taken after receipt of the investigation report: MD
Jalnigam MD Anil Meena told Amar Ujala over the phone that Chief Engineer Sanjay Kumar Singh and Superintending Engineer Jitesh Kumar had been sent to Rae Bareli to investigate the matter. The investigation report has not yet been received. Action will be taken against the person found guilty in the investigation report. He said the roles of XEN, JE and other officials were being investigated by Jalnigam Rae Bareli.

Rae Bareli. The AMRUT program, which was launched to relieve 2.5 lakh residents of the urban area from the sewerage, was commissioned from the start. The work organization Gharpure got the work instead of working, this executive organization gave work to the Tomar Construction Company.

Complaints about the haphazard work were repeatedly reported by the water company to community officials, but the outcome of the operation remained the same. Not only was poor quality pipes used when laying sewers, but poor quality was also used when building roads.

This can be measured by the fact that Rs 67 crore was spent on the system like water, but the system remains the same. The citizens could not be relieved of the sewerage, nor could the streets be speckled.

On Wednesday, not only did the street on Manika Road collapse in the rain, but the lives of passers-by were also saved. The government’s intention was to install a sewer pipe in the city as part of the AMRUT program.

Roads were dug to lay sewers. A budget of Rs 90 crore was made available for this. Approximately Rs 67 crore was spent on the program. Even so, step by step, the plan was messed up.

The road was built in Gora Bazar, but it was in a state of disrepair. The bullets came out. Gribshah was abandoned in the east by building a half-finished road. Jal Nigam and Gharpure Company officials have ever investigated Tomar Construction’s work.

Balmukund Mishra, the EO of the municipality at the time, discovered during several inspections that the pipes laid in the sewer system were of poor quality. The work was stopped. Found a game in road building.

However, later everything was ok. Sunny Singh, XEN of Jalnigam, said that the AMRUT program has received a budget of Rs 90 crore, of which Rs 67 crore has been paid to date.

Sold earth worth lakhs rupees

The officials of the executing organization not only messed up the laying of sewer pipes and construction work, but also sold the land removed during the excavations to the value of lakh. Whether XEN or JE from Jalnigam, none of them paid attention to the standard, but kept filling their pockets. The neglect of the officials has resulted in the flagship of the government of the Amrut Scheme succumbing to corruption in the city.

Actions to be taken after receipt of the investigation report: MD

Jalnigam MD Anil Meena told Amar Ujala over the phone that Chief Engineer Sanjay Kumar Singh and Superintending Engineer Jitesh Kumar had been sent to Rae Bareli to investigate the matter. The investigation report has not yet been received. Action will be taken against the person found guilty in the investigation report. He said the roles of XEN, JE and other officials were being investigated by Jalnigam Rae Bareli.

.

( News Source – Amar Ujala )