2090 heaters torment the people in Majras, could not electrify – 2090 heaters torment people, could not electrify

Pratapgarh. The Saubhagya program, which was set up to shed light on the majors without power, could not be carried out in the district. The electrification could not be completed due to negligence of the work organization. 2090 Majra in the district is still deprived of electricity. They are said to have lit before summer but nothing could be done. Due to a lack of electrification, the people of Majr are upset in the heat.
The Saubhagya program was created to shed light on the majors without power. 2018 marked the underprivileged Mazars under the program. A list of about six thousand such majors was drawn up in the district. A budget of 398 crores has been approved for electrification. The Bajaj Company took responsibility for the electrification. In the initial stages, the work went quickly, but later the contractors began to be negligent. When the timeline ran out, officials began to investigate and reprimand the work, but even after that, the work of more than 2,500,000 majras could not be completed.
Among them were about 500 majra that could not start the power supply due to lack of equipment. Following the complaint from public officials, officials began investigating them, and then the executive body’s poll was revealed. Officials from Varanasi and Lucknow strongly reprimanded the contractors. Instructions were given to complete the electrification work before summer, but the work remained incomplete even after that. Because of the negligence and indecency of officers, people with majors without power are now molested. People have to go to other majors to top up cell phones as well. People have complained about this to public officials too often, but nothing could be done. Superintendent Engineer Satyapal announced that the work where the work was incomplete has been completed. A list of 2090 majors who have been deprived of electricity has been drawn up. The proposal has been sent.
The pole is standing, the line could not be ready
The entire Bachil village of Bhupiamau failed to complete the Saubhagya scheme electrification. There are Poles in the village, but the border could not be drawn. Department officials claim to have completed the electrification work which is incomplete in the electricity shortage majors, but there are only poles in the village. Even after two years there is no electricity in the village. A complaint was also filed with the Chief Minister.

Pratapgarh. The Saubhagya program, which was set up to shed light on the majors without power, could not be carried out in the district. The electrification could not be completed due to negligence of the work organization. 2090 Majra in the district is still deprived of electricity. They are said to have lit before summer but nothing could be done. Due to a lack of electrification, the people of Majr are upset in the heat.

The Saubhagya program was created to shed light on the majors without power. 2018 marked the underprivileged Mazars under the program. A list of about six thousand such majors was drawn up in the district. A budget of 398 crores has been approved for electrification. The Bajaj Company took responsibility for the electrification. In the initial stages, the work went quickly, but later the contractors began to be negligent. When the timeline ran out, officials began to investigate and reprimand the work, but even after that, the work of more than 2,500,000 majras could not be completed.

Among them were about 500 majra that could not start the power supply due to lack of equipment. Following the complaint from public officials, officials began investigating them, and then the executive body’s poll was revealed. Officials from Varanasi and Lucknow strongly reprimanded the contractors. Instructions were given to complete the electrification work before summer, but the work remained incomplete even after that. Because of the negligence and indecency of officers, people with majors without power are now molested. People have to go to other majors to top up cell phones as well. People have complained about this to public officials too often, but nothing could be done. The Superintendent Engineer Satyapal announced that the work on which the work was incomplete has been completed. A list of 2090 majors who have been deprived of electricity has been drawn up. The proposal has been sent.

The pole is standing, the line could not be ready

The entire Bachil village of Bhupiamau failed to complete the Saubhagya scheme electrification. There are Poles in the village, but the border could not be drawn. Department officials claim to have completed the electrification work which is incomplete in the electricity shortage majors, but there are only poles in the village. Even after two years there is no electricity in the village. A complaint was also filed with the Chief Minister.

.